Locheed-Martin Plant, Goodyear, Arizona

The project encompassed 1.6 million square feet of space in 92 buildings, on 168 acres of land. The site assessment included an onsite electrical sub-station, a potable water plant, a self-contained fire sprinkler system and a wastewater treatment plant. Project completion time: 4.5 weeks

MFD & Company, Houston, Texas

The project involved the inspection of eight different industrial parks with 48 buildings, totaling 1.4 million square feet of space. Project completion time: 2.5 weeks

MFD & Company, Phoenix, Arizona

The inspection projet was comprised of three apartment complexes, with a total of 74 three story apartment buildings with 1,180 apartment units and associated garages. Project completion time: 3 weeks

Environmental Assessments

National/Alamo Car Rental, Phoenix, Arizona

The project involved the excavation and removal of five underground fuel and oil storage tanks, soil sampling and the subsequent cleanup of contaminated soil.

American Metals, Phoenix/Mesa, Arizona

The scope of services included soil assessment for contaminants, excavation, stabliization of contaminants, and removal & disposal of contaminated soil on two sites.

Estrella Mountain Ranch/Newland Companies, Phoenix, Goodyear, Buckeye, Arizona

Phase I Environmental Assessments, approximately 50, on properties from 1 acre to in excess of 20,000 acres per site.

Pacific Realty Advisors, Phoenix, Arizona

Phase I Environmental Assessment of the Motorola semiconductor plant in Mesa, and subsequent follow-up consulting on the demolition of the site.

Construction Progress Inspection Reports

Chaparral Animal Hospital, Cave Creek, Arizona

Ground up construction oversight on $3.3 million dollar development

Single Family Residence – Silverleaf Subdivision, Scottsdale, Arizona

Ground up construction oversight on $7.7 million dollar residence

Papago Golf Course Renovation, Phoenix, Arizona

Renovation oversight of 18 hole golf course including tree removal, pond redevelopment, re-sloping of fairways, new greens, tee boxes and hazards. $5.7 million dollar project.